Apply a textured facade coating in four controlled stages: verify the render is cured and dry below 5% moisture, prime the full elevation, apply the coating wet-on-wet across a complete elevation without stopping mid-wall, then texture with a consistent float technique before the surface skins. Work out of direct sun and keep one applicator per elevation to avoid shade variation.
Materials
- —Penetrating primer (e.g. Terrabond A / P Primer Clear)
- —Textured facade coating in the specified grain
- —Protective topcoat or stain where specified
- —Clean potable water
Tools
- —Stainless steel trowel and plastic float
- —Hopper gun and compressor (spray-applied grades)
- —Mixing drill with paddle, 600 rpm
- —Moisture meter
- —Masking tape, scaffold, shade netting
Step-by-step procedure
- 1
Check substrate readiness
Allow cementitious render at least 28 days to cure. Test moisture with a meter — below 5% — and check for laitance, dust, form oil, cracks and hollow areas. Repair defects and let repairs cure before proceeding.
- 2
Mask, protect and plan the elevation
Mask windows, sills and joinery. Erect shade netting where the elevation faces afternoon sun. Divide the facade only at natural breaks — corners, movement joints, downpipes — never mid-wall.
- 3
Prime the whole surface
Roll or brush one even coat of penetrating primer to bind dust and equalise suction. Do not thin beyond the data sheet limit. Allow the full recoat interval, typically 4–6 hours in Dhaka conditions.
- 4
Mix the coating
Stir each pail with a slow-speed paddle for 2–3 minutes. Box together pails of the same batch for one elevation so pigment variation cannot show as banding. Add water only within the stated tolerance.
- 5
Lay on to grain thickness
Trowel or spray the coating to the thickness of the largest aggregate — a thinner film will not texture, a thicker one will craze. Keep a wet edge and have a second applicator feeding material so the leading edge never dries.
- 6
Texture consistently
Float the surface in the specified pattern — circular, vertical drag or travertine — using the same pressure and direction across the elevation. One applicator should texture an entire elevation, even if two lay on the material.
- 7
Cure and protect
Protect from rain for at least 24 hours and from direct sun during the first hours of set. Remove masking while the coating is still fresh to avoid pulling edges.
- 8
Topcoat and inspect
Apply the specified topcoat or stain after full cure. Inspect the elevation in raking light from ground level and from an opposite building to catch banding before scaffolding is struck.
Weather windows in Bangladesh
Do not apply below 5 °C or above 35 °C surface temperature, in relative humidity above 85%, or when rain is forecast within 24 hours. During monsoon, plan elevations around the daily rain pattern and keep sheeting ready.
Common site mistakes
Stopping a coat mid-wall for a tea break, mixing batches from different production lots on one elevation, over-watering to make trowelling easier, and priming only the patched areas are the four defects that cause most facade rejections.
Related articles
Explore matching systems
Reviewed by
Sabbir Ahmed
Applications & Training Manager
Terraco-certified applicator trainer, 15 years site experience
See our technical advisory panelStandards referenced
- —EN 1504-10: Site application of products and quality control