Calculate quantity as: net coated area × number of coats ÷ practical coverage rate, then add a wastage allowance of 5% for rolled paint, 10% for trowelled texture and 15–20% for spray application. Use the practical (site) coverage rate, not the theoretical one, and never deduct openings smaller than 2 m² because reveals consume the same material.
Materials
- —Product data sheets with coverage figures
Tools
- —Measuring tape or laser distance meter
- —Elevation drawings
- —Spreadsheet
Step-by-step procedure
- 1
Measure gross area
Take each elevation length × height from drawings and verify on site. Keep elevations separate so ordering matches the batching plan.
- 2
Adjust for openings
Deduct openings larger than 2 m² only, and add reveal areas (perimeter × depth) back in. Small windows are treated as solid wall.
- 3
Pick the practical coverage rate
Data sheets quote theoretical coverage on a smooth substrate. Reduce it by 10–25% for rough render, high-suction block or heavy texture. For textured coatings use kg/m² per grain size, not litres.
- 4
Multiply by coats
Count every layer in the system: primer, basecoat, texture, topcoat. Each has its own coverage rate — calculate them as separate line items, not one blended figure.
- 5
Add wastage and a control batch
Add 5% for roller, 10% for trowel, 15–20% for spray, plus scaffold losses. Order one extra pail of the same batch per colour and store it for later touch-ups.
- 6
Reconcile on site
Record actual consumption per elevation against the calculation. Consumption far below plan usually means the film is too thin — a warranty risk, not a saving.
Worked example
A 400 m² facade with a 1.5 mm textured coating at a practical rate of 2.5 kg/m²: 400 × 2.5 = 1,000 kg, plus 10% trowel wastage = 1,100 kg. Primer at 8 m²/L for one coat: 400 ÷ 8 = 50 L, plus 5% = 53 L.
Order in whole batches
Round up to full pails and, for coloured products, ask for a single production batch per elevation. Mixing batches mid-wall is a common cause of visible shade differences.
Related articles
Explore matching systems
Reviewed by
Sabbir Ahmed
Applications & Training Manager
Terraco-certified applicator trainer, 15 years site experience
See our technical advisory panelStandards referenced
- —EN 1504-10: Site application of products and quality control
- —Terraco technical datasheets and application manuals
Need a specification?
Our technical team supports architects, contractors and applicators across Bangladesh from the Dhanmondi Experience Center.