Wiki

How to waterproof a bathroom before tiling

Waterproofing · 6 min read

Waterproof a bathroom by preparing and repairing the screed, forming a fall of at least 1:100 to the drain, filleting all wall-floor junctions, taping every corner and penetration, applying two cross-directional membrane coats to the full wet area and 1.8 m up shower walls, then flood testing for 24 hours before any tile adhesive is used.

Materials

  • Cementitious or flexible waterproof membrane (e.g. Terraseal)
  • Reinforcing tape for corners and junctions
  • Polymer bonding primer
  • Non-shrink repair mortar for fillets

Tools

  • Angle grinder or scabbler for laitance removal
  • Block brush and 4 mm notched trowel
  • Spirit level or laser for fall check
  • Bucket, paddle mixer

Step-by-step procedure

  1. 1

    Strip and inspect

    Remove old finishes back to sound screed or concrete. Check for cracks, honeycombing and loose sand-cement. Confirm all plumbing rough-in is complete and pressure tested — no penetration may be cut after waterproofing.

  2. 2

    Correct the falls

    Verify a minimum 1:100 fall towards the floor waste, and 1:80 inside a shower area. Re-screed flat or ponding areas; a membrane cannot compensate for standing water.

  3. 3

    Form fillets and repair

    Cut out cracks, fill with repair mortar, and form a 25 mm cove fillet at every wall-floor junction so the membrane is never asked to turn a sharp 90° angle.

  4. 4

    Prime the substrate

    Dampen or prime per the membrane data sheet. Cementitious membranes usually need a saturated surface-dry substrate; acrylic ones need a fully dry, primed one.

  5. 5

    Band the movement points

    Bed reinforcing tape into a wet first pass of membrane at all internal corners, wall-floor junctions, drain flanges and pipe penetrations. This detail is where nearly all wet-area leaks begin.

  6. 6

    Apply two coats

    Brush the first coat over the full floor and up walls to 1.8 m in showers and 150 mm elsewhere. Once touch-dry, apply the second coat at right angles to the first to eliminate pinholes. Respect the total wet film thickness in the data sheet.

  7. 7

    Flood test

    After full cure, plug the drain, flood the floor to 25 mm and hold for 24 hours. Check the ceiling and walls below. Only a passed flood test releases the area for tiling.

  8. 8

    Tile with a compatible adhesive

    Use a polymer-modified C2 adhesive over the membrane. Never mechanically fix through the membrane; if a fixing is unavoidable, seal it with membrane and tape.

Why the flood test is not optional

Rectifying a leaking wet area after tiling costs many times the price of the membrane. A documented 24-hour flood test with photographs is the cheapest insurance on a project.

Related articles

Explore matching systems

Reviewed by

Engr. Mahmudul Hasan

Technical Director, Terraco Bangladesh

B.Sc. Civil Engineering (BUET), Chartered Member IEB

See our technical advisory panel

Standards referenced

  • EN 14891: Liquid-applied water impermeable products for use beneath ceramic tiling
  • EN 1504-2: Surface protection systems for concrete